鋼筋加工棚是如何搭建的?
來(lái)源:http://www.vizajist.net/ 發(fā)布時(shí)間:2021-09-30
鋼筋作為建筑施工的主要材料,大多數需要在施工現場(chǎng)進(jìn)行加工操作,操作人員在施工現場(chǎng)的工作時(shí)間也相對較長(cháng),為了改善操作環(huán)境,鋼筋加工棚應運而生。鋼筋加工棚是施工現場(chǎng)內對鋼筋進(jìn)行拉直、彎曲、焊接等鋼筋加工作業(yè)的場(chǎng)地。
As the main material of building construction, most of the reinforcement needs to be processed on the construction site, and the operators have a relatively long working time on the construction site. In order to improve the operating environment, the reinforcement processing shed came into being. The reinforcement processing shed is the site for straightening, bending, welding and other reinforcement processing operations on the construction site.
現場(chǎng)鋼筋加工棚一般需根據施工組織計劃,安置鋼筋對焊機、切斷機、彎曲機、調直機等設備的數量及加工流水線(xiàn);另還需考慮部分鋼筋原材料、加工后鋼筋的周轉及堆放;現場(chǎng)施工場(chǎng)地、用電等條件來(lái)確定。
The on-site reinforcement processing shed generally needs to place the number of reinforcement butt welding machines, cutting machines, bending machines, straightening machines and other equipment and processing lines according to the construction organization plan; In addition, the turnover and stacking of some reinforcement raw materials and processed reinforcement shall be considered; Site construction site, power consumption and other conditions.
哪些場(chǎng)所必須搭建加工棚
Which places must build processing sheds
1.施工現場(chǎng)所有鋼筋加工場(chǎng)均需設置加工棚,
1. All reinforcement processing yards on the construction site shall be provided with processing sheds,
2.所有露天放置的施工設備均應搭設防護棚,如木工加工、小型機械、攪拌機、砂漿機等。
2. All construction equipment placed in the open air shall be provided with safety protection sheds, such as woodworking, small machinery, mixer, mortar machine, etc.
3.在建筑物墜落半徑內或塔吊覆蓋范圍內的加工棚需要設置雙層硬質(zhì)防護。
3. The processing shed within the falling radius of the building or within the coverage of the tower crane needs to be provided with double-layer hard protection.
鋼筋加工棚搭建要求
Construction requirements of reinforcement processing shed
1.工具式鋼筋加工棚搭設具體尺寸根據現場(chǎng)實(shí)際情況確定。
1. The specific size of tool type reinforcement processing shed shall be determined according to the actual situation on site.
2.搭設在塔吊回轉半徑和建筑物周邊的加工車(chē)間必須設置雙層硬質(zhì)防護。
2. The processing workshop set up around the slewing radius of the tower crane and the building must be provided with double-layer hard protection.
3.加工區地面需硬化,宜選用混凝土地面。
3. The ground of the processing area needs to be hardened, and the concrete ground should be selected.
4.加工區頂部應張掛警示標識和宣傳用語(yǔ)的橫幅,橫幅寬度宜為1米。
4. Safety warning signs and banners of safety propaganda words shall be hung on the top of the processing area, and the width of the banner should be 1m.
5.工具式鋼筋加工棚需在醒目處掛操作規程圖牌,圖牌的尺寸為:寬×高=2m×1mm。
5. The tool type reinforcement processing shed shall hang the operation specification drawing board at an eye-catching place, and the size of the drawing board is: width × Height = 2m × 1mm。
6.各種型材及構配件規格為參考值,具體規格應根據當地風(fēng)荷載、雪荷載進(jìn)行核算。
6. The specifications of various profiles and components and fittings are reference values, and the specific specifications shall be calculated according to the local wind load and snow load.
7.南方地區,如遇臺風(fēng)應采取防風(fēng)措施,可設置纜風(fēng)繩。
7. In case of typhoon in southern China, windproof measures shall be taken, and wind ropes can be set.